Client Alerts
Launch of new FIDIC contract conditions
The International Federation of Consulting Engineers (commonly known as FIDIC, acronym for Fédération Internationale Des Ingénieurs-Conseils) launched its much anticipated 2017 FIDIC Suite of Contracts at its annual users’ conference which took place on 5 and 6 December 2017 in London. FIDIC has published revised versions of its internationally recognized "Rainbow Suite", namely the Red Book (Building and Engineering Works), the Yellow Book (Plant and Design-Build) and the Silver Book (EPC/Turnkey Projects).
FIDIC’s new 2017 conditions of contract replace the renowned FIDIC 1999 Suite of Contracts which governed many of the world’s high-profile construction and infrastructure projects due to the flexible and adaptable approach of the FIDIC model contracts across several jurisdictions. As such, the FIDIC conditions of contract are currently – and will certainly remain – the "contract of choice" for international infrastructure and process plant projects, particularly in Eastern Europe, Africa, the Middle East and Asia.
The newly released contracts reflect a long-awaited update and response to the changing needs of the construction industry. In doing so, FIDIC adopted best practices and international standards in preparing the FIDIC books to reflect the challenges construction contracts face in a quickly developing and highly digitalized future. The new, more prescriptive 2017 FIDIC books now consist of 21 clauses of General Conditions of Contract rather than 20, and include far-reaching amendments compared to the 1999 model provisions. The core aim of the majority of changes is increased clarity and certainty to reduce the risk of disagreements and thereby increase the probability of successful projects. In particular, the following modifications will have the largest impact on parties to international construction agreements based upon the FIDIC books:
In our next client alerts we will keep you updated on those issues which require particular attention in contract negotiations, claim management and arbitration in international construction contracts and construction disputes.
Download PDF
Download PDF
Download PDF
Download PDF
Download PDF
Download PDF
Download PDF
Download PDF
Download PDF
Download PDF
Download PDF
Download PDF
Download PDF
FIDIC’s new 2017 conditions of contract replace the renowned FIDIC 1999 Suite of Contracts which governed many of the world’s high-profile construction and infrastructure projects due to the flexible and adaptable approach of the FIDIC model contracts across several jurisdictions. As such, the FIDIC conditions of contract are currently – and will certainly remain – the "contract of choice" for international infrastructure and process plant projects, particularly in Eastern Europe, Africa, the Middle East and Asia.
The newly released contracts reflect a long-awaited update and response to the changing needs of the construction industry. In doing so, FIDIC adopted best practices and international standards in preparing the FIDIC books to reflect the challenges construction contracts face in a quickly developing and highly digitalized future. The new, more prescriptive 2017 FIDIC books now consist of 21 clauses of General Conditions of Contract rather than 20, and include far-reaching amendments compared to the 1999 model provisions. The core aim of the majority of changes is increased clarity and certainty to reduce the risk of disagreements and thereby increase the probability of successful projects. In particular, the following modifications will have the largest impact on parties to international construction agreements based upon the FIDIC books:
- The former Clause 20 [Claims, Disputes and Arbitration] has been split into Clause 20 [Employer’s and Contractor’s Claims] and Clause 21 [Disputes and Arbitration] to separate ‘day-to-day’ Parties’ claims from Parties’ disputes. To highlight the distinction in the contractual approach, Employers’ Claims are no longer part of Clause 2 since these are now dealt with in Clause 20 in the same way as Contractors’ claims;
- Sub-Clause 3.7 [Determinations] of the Red and Yellow Books 2017, which replaces Sub-Clause 3.5, details the Engineer’s role in dealing with Parties’ claims and introduces a step-by-step procedure with time limits;
- Sub-Clause 8.3 [Programme] has been updated with additional requirements for the initial programme and all revised programmes to be submitted to the Engineer (under the Red and Yellow Books 2017) or to the Employer (under the Silver Book 2017), i.e. the critical path and any float or linked activities, key delivery dates for plant and materials, as well as any delays and the sequence and timing of remedial works shall be displayed;
- Sub-Clause 20.2 [Claims for Payment and/or EOT] prescribes the step-by-step procedure to be followed for Employers’ and Contractors’ claims for time and/or money. If the Engineer (under the Red and Yellow Books 2017) or the other Party’s (under the Silver Book) initial response is that the Notice of Claim is time-barred due to the 28 day time-bar provision, but the claiming Party disagrees, the claiming Party is required to include these points in the fully detailed claim and these need to be taken into account in the agreement/determination;
- Sub-Clause 21 [Constitution of the DAAB] provides for a "standing" Dispute Avoidance/Adjudication Board (DAAB), i.e. the board is appointed at the start of the Contract and is in place for the duration of the Contract; furthermore, the procedure to obtain the DAAB’s decision and a Party’s failure to comply with such decision has been clarified in Sub-Clauses 21.4 [Obtaining DAAB’s Decision] and Sub-Clause 21.7 [Failure to Comply with DAAB’s Decision].
In our next client alerts we will keep you updated on those issues which require particular attention in contract negotiations, claim management and arbitration in international construction contracts and construction disputes.
Read the full text
Read the full text
Read the full text
Read the full text
Read the full text
Read the full text
Read the full text
Read the full text
Read the full text
Read the full text
Read the full text
Read the full text
Read the full text